Sunday, August 12, 2012

Up she goes!

     Out of the ground and underway.  Brent and his crew started framing last week.  The Smart framing techniques have prove a little challenging, keeping studs joists and rafters aligned.  Also correct header sizing, everybody wants to keep adding a safety factor instead of trusting the numbers.  We're working throught that and the other thing that we have to keep checking is the Energy Star Thermal Bypass checklist for anything going on the exterior walls.  For instance Jeff made a good catch earlier this week noting that "Don't we need to have an air barrier going around the stairs?" This just before they started framing in the stairs!  The learning curve has been a little steep for everyone.  People are a little jumpy around the site hoping they haven't missed something that would cost a point or worse a pre-requisite.

     I've attached a few pictures to show some of the framing.  Another item to note is the use of Structural Insualted Sheathing (SIS) instead of OSB.  The 1/2" SIS gives us an additional R-3 after the foam has stabilized.  Over this we will be placing another 2" of Poly-iso foam rated at R-12, then housewrap, then 3/4" furring strips to mount the siding on.  The use of two layers of foam insulation  and offsetting the seams during installation, significantly decreases the amount of air infiltration.  Also in typical construction with OSB as the sheathing and fiberglass ("filterglass") insulation in the wall cavity, creates a situation where the back side of the OSB is warmer than the exterior face thus creating a surface for condensation to collect.  OSB + Condensation = a bad situation over time if the OSB does not have adequate time and air flow to dry out.
    



     Right now, I'm pretty well exhausted.  Building this house is fun even if it is a little draining mentally.  But not only are we building the house, I'm trying to get the pavilion started, we're looking at rescuing a couple of old barns to re-locate to the farm and I have a stone chicken coop to build before winter.   Yeesh!  I'll keep more coming. 

Wednesday, July 11, 2012

Ok so it have been awhile and a lot has happened since the last post.

First thing is we changed General Contractors.  Tom is still doing the site work at the farm but Tom Doyle of Doyle Home is now the GC.  Jeff is a custom home builder with 20+ years of experience.  Again no "Green" experience but he has really taken on the challenge and things are moving forward at a fast pace.

Secondly, if you remember we were shooting for an initial HERS (Home Energy Rating System) score of about 40 points.  Keep in mind the average resale home in the United States scores about 130.  A score of 100 is considered the average for new construction built to code.  So an existing home, as an example, is roughly 30% more inefficient than a new home.  So a score of 40 would theoretically make our house 60% more efficient than a new home.  The score is derived from an energy model created by the HERS rater.  The model takes into account all of the wall components, roof components, window U-factors, energy used by appliances etc.  We were then able to utilize the energy model to try out different insulation and material combinations to achieve the best energy efficiency and most bang for the buck.

Having said all of that, our preliminary HERS rating is a 41!  Kudos to the design team and thanks to Scott and Alex for working with us to get the information to us in a timely fashion so we could make our decisions!

Thirdly, we started digging today!  we've got a big hole in the ground but the foundation looks more like a foundaiton for an outhouse with a basement!  Somehow we'll fit.  It's certainly larger than the fifth wheel we're currently in!

As  a side note check  out the pictures from Horse Progress Days.   This was in Clare, MI a couple of weeks.  Two days devoted to Horse Power and the economic viability of horses for use on small farms.  It was a ton of fun, unfortunately my pictures of the 12 horse team didn't take!

Anyway, more to come, we're getting to the good stuff!


House features

Back again!  So here are some of the features of the house.

   The house is small, 32' x 24' footprint that equates to 1536 sf of conditioned space.  We kept the footprint small for several reasons.  First a larger house means we have to buy more stuff to fill it up thus reducing the Funstuff Funds.  We'd rather go play than buy another sofa.  Secondly, if we keep it small we can add other features to the house, LEED certification for instance.  Lastly, LEED rewards smaller homes.  Not suprisingly larger homes consume more resources, not just building materials but also heating and cooling.  They award smaller designs through the Home Size Adjuster (HSA).

   Based on informal studies and published data, within the context of LEED, a 100% increase in home size equates to an increase in annual energy usage of 15% - 50%, depending on the region.  Also the same increase equates to an increase in materials usage of 40% - 90% depending on the design.  So smaller homes can earn extra points towards certification based on the number of bedrooms and square footage.  So the SCF house will 5 points based on the square footage and bedrroms.

   We've tried to keep as many penetrations out of the exterior walls as possible.  You'll notice that the only fixture mounted on an exterior wall is the sink in the Master bath.  Believe me we tried every possible combination to get it off the wall.  The reason we kept out of the exterior walls is that every penetration is a potential air leak.  Air moving inside the thermal barrier sets up all kinds of potential problems with moisture in the walls as well as reducing the efficiency of the walls.

   "Smart Framing" will also be utilized in the construction.  Smart framing incorporates techniques such as aligning roof trusses and wall studs so that the trusses bear directly on the studs.  This eliminates the need for a second top plate on the wall.  Also no headers in non-load bearing walls, sizing headers to the exact size needed, studs and rafters spaced greater than 16" on center and no trimmer studs at window and door openings.  All of this amounts to significant reductions in the amount of wood needed top build the house.  Also less wood in the walls means more room for insulation.





 Well lunch is over, back to the grind.  More to follow.

Tuesday, May 1, 2012

Design Review

  Alright, alright so it's been a few days, ok weeks since my last post.  My apologies.  What with trying to get hoop houses built, researching and tracking down products, things have been pretty hectic.  The good part is now I have some images to share of our proposed floor plan and a couple of elevations.

  We finished up our design charrette last week with Dave from Lindhout, Tom Boyle, John Boylan of Lakeside Services (HVAC), Tom and Shannon Rau, Joannee and I and our Green Rater, Alex.  We had a really good meeting lots of good discussion about mechanical systems and photovoltaics.  The house has undergone a few iterations since the initial charrette and as a result we hope to pick up 5 more points toward our LEED certification.  But I won't get into the geeky stuff tonight.  I would like to talk the house and maybe some about our product selections so far.

You can see we retained the small footprint of the house, it took a few heart to heart discussions but with some design help from Joannee, Dave and Piet were able to draw out a really fun floorplan on the first floor without expanding the size of the house.  This is important to us because more space means having to spend more money to fill it up, heat it, cool it and clean it 
  1. Tulikivi masonry heater is the centerpiece here, literally.  Locating the heater in a central location and with very few walls will allow us to use this as the primary heat source in the winter.  This is a soapstone behemoth weighing in at over 5000 lbs.  The soapstone absorbs the heat from the fire and slowly radiates the heat outward over time.  A 1 1/2 hour burn twice a day will heat the house for about 24 - 30 hours.  Possibly longer with the R-35 walls.
  2. Reclaimed wood flooring throughout the house upstairs and down.  We are looking at maple or possibly locust.
  3. Recycled brick in the mudroom coming from the garage.  The mudroom was originally going to be the space between the garage and main house.  Thanks to a little sleight of hand from Dave we were able to increase the size of the room in the house.  The original mudroom now becomes a breezeway and a home for the grill.  Also becasue the garage is detached from the house, this improves the indoor air quality and scores 3 points for LEED.  Durability is also a LEED consideration and we have developed a project specific durability checklist.
  4. The kitchen is on the south side of the house.  In order for the house to benefit from solar orientation LEED requires 40% of the total glazing area to be on the South side.  A challenge when you have a small house, a fairly steep roof and countertops to work around!  Again, Dave sneaks in the round window in the upstairs bedroom to eek us over the line. We are considering two manufacturers Accurate Dorwin made in Canada and Serious Windows, made in California,  Both exceed Energy Star ratings by almost double.
  5. All appliances in the house will be Energy Star rated.  Hopefully we will be able to reduce our electrical load in the house enough to make solar power feasible.
Ok it's late, I'll add more tomorrow.  Oh wait, I said that last month.



Thursday, March 8, 2012

LEED Design Charrette


Well we got through our design charrette today.  For those of you who may be unfamiliar with this term, charrette comes from the French for a wagon or carriage.  Back in the day, French architectural students would cram into the carriage and would work madly to finish their sketches before arriving at class.  Today a design charrette is a day of brainstorming and throwing ideas out on the table for discussion.  For the purposes of LEED it the day when the team considers all of the available points that can be pursued, and they rate which points are achievable, not achievable and those maybe points that are worthy of further consideration.


Integrated Design
The key to making this work is having as many people from the project team present as is possible.  Today we had Dave from Lindhout Architect's present, as well as Tom and Joannée from Stone Coop, myself as Owner's rep, Tom Boyle our builder, Mike from Alliance for Environmental Sustainability, Alex our Green Rater, Scott our HERS rater/energy modeler, John Boylan from Lakeside Heating & Cooling and Brent Deline our framing  contractor.  Everybody had a chance to comment on the credits and discuss possible strategies.


The idea in getting everyone on board early is to have the team influence the design early on rather than reacting to design on the jobsite.  Everyone has a clear understanding of the goals early on and they have had an opportunity to discuss how all of the parts and pieces go together.  Rather than the old fashioned way, getting to the jobsite and having several people scratching their heads trying to figure out what the designers were trying to accomplish.


The Checklist
I don't have a final copy of the checklist yet but I will post as soon as I do.  We were shooting for a number in the 70's which would put us solidly in the Gold category.  We ended up at 84 pts only 6 points away from Platinum.  We have a fair number of points in the maybe column that we can pull on for the other 6.


Here's a short list of some of the major strategies we are attempting:

  1. Smart Framing - We'll be using 2x6 stud walls spaced 24" on center.  This will allow fewer studs in the wall which increases the area for insulation and uses less wood.  Also part of this framing method is to not double up on studs around windows and doors (trimmer studs) and to properly size headers for the anticipated load and on non-load bearing walls you don't use a header.
  2. Outsulation v. Insulation - We will be using a 1/2" structural insulated sheathing on the exterior walls, no osb, with and additional 2" of R-10 rigid foam insulation over that.  We're shooting for an R-30, R-35 wall.  All seams will be taped or glued to create a really tight air barrier.  The problem with wood on the exterior of the structure is that when the house is warm in the winter, the wood sheathing is warm on one side and cold on the other.  This creates a place for water vapor to collect.  With a long enough summer and good ventilation the sheathing will dry. But enough cycles of this creates a potential problem.  We're still discussing the wall cavity insulation.
  3. Roof Insulation - The roof will consist of a foam insulation sealing the truss chords and the ceiling drywall.  Then we will blow in insulation over that.  We are shooting for approximately R50 in the roof.
  4. Heating/Cooling - Ductless heat pump system.  Very high efficiency, SEER 18, and no duct work.  There is a condensor unit located on the exterior of the house and then 3 - 4 fan units inside.  A Tulikivi masonry heater.  Essentially a 3,000 lb soapstone fireplace that, with 2 hours of burn time, will radiate heat for 24 hours.
These are just some of the items we are including in the house.  We will also have re-claimed wood flooring, low or no VOC paints, sealants and adhesives, buying materials with 500 miles of the jobsite just to name a few.


I'll get some more up this week end.  I'll try and get more photos up as well.


                                    
Joannée as architect.





Sunday, February 26, 2012

Up and (not quite) Running

Greetings and welcome to the site!  This is my first attempt at this blogging thing so bear with me while i get my sea legs under me.

     The primary purpose of this site is to keep everyone informed of the changes occurring at the Musch Rd site, follow the farm's progress as they pursue LEED certification for the new home that will be built on the property and to engage in a discussion about sustainable construction and efficient buildings.  I hope you will add your thoughts and comments as we move forward.
     The farm's building partners for this endeavor will be Piet Lindhout and Dave Richardson of  Lindhout Architects, General Contractor will be Tom Boyle of Tom Boyle Building and the Owner's Representative will be me and the newly formed 3 Pillars Construction LLC.  We hope to have most of the construction team on board within the next month or so.
    So far we have developed the site plan and if you have been by the site you have already seen some of the stakes laying out parts of the driveway, the pavilion and the house.  We are meeting Thursday to see the first sketches of the floor plan.  We are also having a LEED design charrette on the 8th of March to develop our LEED points checklist.  I'll be adding a post related to all things LEED; the goals of LEED certification, the process, and credit requirements.

   In the interest of brevity (a condition I struggle with) I'm going to end here so I can collect my thoughts and call Shannon so she can explain to me how to actually manage this site!  Stay tuned, lots more to come.
Aerial view: Musch runs N and S,
Spicer running E and W.